Progress for 2018 Investment Programme The Investment Programme of IDGC of the South for 2018 was approved by Order of the Ministry of Energy of Russia dated November 15, 2018.
| Branch of IDGC of the South | CAPEX, RUB mn (excl. VAT) | Fixed assets commissioned, RUB mn (excl. VAT) | Financing, RUB mn (incl. VAT) | Capacity commissioned | |
|---|---|---|---|---|---|
| MVA | km | ||||
| Astrakhanenergo | 412 | 394 | 507 | 17 | 207 |
| Volgogradenergo | 454 | 341 | 284 | 6 | 24 |
| Kalmenergo | 62 | 92 | 76 | 2 | 59 |
| Kubanenergo | 1 | 1 | 2 | ||
| Rostovenergo | 1,142 | 1,391 | 1,244 | 27 | 256 |
| Executive office | 3 | 0 | 0 | ||
| Total | 2,075 | 2,219 | 2,112 | 52 | 545 |