Progress for 2018 Investment Programme The Investment Programme of IDGC of the South for 2018 was approved by Order of the Ministry of Energy of Russia dated November 15, 2018.
Branch of IDGC of the South | CAPEX, RUB mn (excl. VAT) | Fixed assets commissioned, RUB mn (excl. VAT) | Financing, RUB mn (incl. VAT) | Capacity commissioned | |
---|---|---|---|---|---|
MVA | km | ||||
Astrakhanenergo | 412 | 394 | 507 | 17 | 207 |
Volgogradenergo | 454 | 341 | 284 | 6 | 24 |
Kalmenergo | 62 | 92 | 76 | 2 | 59 |
Kubanenergo | 1 | 1 | 2 | ||
Rostovenergo | 1,142 | 1,391 | 1,244 | 27 | 256 |
Executive office | 3 | 0 | 0 | ||
Total | 2,075 | 2,219 | 2,112 | 52 | 545 |