Grid Connection
Under Decree No.147-r of the Government of the Russian Federation dated January 31, 2017, IDGC of the South implemented the Grid Connection target model in each covered regions in cooperation with regional executive authorities to simplify business processes and enhance the investment appeal of the Russian Federation constituent entities.
In 2018, the Company arranged:
- Roadmap activities on the implementation of the target model with the grid organisation as a responsible party, and the submission of branches’ quarterly reports to the regional executive bodies;
- Interaction with the regional executive bodies to take the necessary measures on implementing indicators of the roadmaps, achievement of which target indicators are under the responsibility of relevant ministries and municipal entities.
With a view to reaching the indicators of the Grid Connection target model, the Company developed and approved the order On Grid Connections of Doing Business Applicants. In the reporting year, the Company fulfilled 90 contracts for grid connection of Doing Business applicants. Rostovenergo provided power supply to 46 such enterprises, Astrakhanenergo connected 21 consumers, Kalmenergo and Volgogradenergo provided grid connection of 12 small business enterprises each.
Over 130 socially significant facilities with a total capacity of above 3.8 MW were connected to the distribution grid of IDGC of the South in 2018. Among them:
- Remontnaya (Dubovsky District), Kolodezi (Millerovsky District), Kuteynikovo (Chertkovsky District) traction substations of Russian Railways (Rostov Region) – the required capacity was 57 MW; increase in power output of Rostov TPP-2 and the Central Boiler House of Rostov-on-Don;
- Rostov Arena stadium with 14 MW connected capacity;
- the waste recycling plant in Volgograd’s satellite town - Volzhsky, which will recycle up to 450 thous. tonnes of wastes a year and consume 1 MW of power;
- five solar power stations in the Astrakhan Region with a total capacity of above 100 MW;
- the kindergarten for 260 children in Sanatorny residential complex in the Volgograd’s Kirovsky District with the connected capacity of 280 kW;
- the grain warehouse in the Volgograd’s Leninsky District, warehouses of oil and gas equipment manufacturer.
Category of applicants | Applications | ||||
Quantity | For capacity | ||||
pcs | % | kW | % | ||
Individuals | Up to 15 kW | 13,710 | 71 | 143,686 | 6 |
Small Business | Up to 15 kW | 2,891 | 15 | 24,223 | 1 |
Over 15 to 150 kW | 1,838 | 9 | 131,372 | 6 | |
Medium business | From 150 to 670 kW | 392 | 2 | 120,280 | 5 |
Large business | 670 kW and above | 540 | 3 | 1,889,357 | 82 |
Total | 19,371 | 100 | 2,308,919 | 100 |
Sector of the national economy | Quantity | |
pcs | kW | |
Individuals | 13,710 | 143,686 |
Agriculture, hunting, forestry, fishery, fish farming | 350 | 138,118 |
Extraction of mineral resources | 13 | 6,808 |
Processing industries | 356 | 236,736 |
Production and distribution of electricity, gas and water; air conditioning (35.11. Electricity Generation and Subsections) | 16 | 740,345 |
Production and distribution of electricity, gas and water; air conditioning (35.12.1. Power Transmission and 35.13. Electricity Transmission and Distribution) | 13 | 7,934 |
Production and distribution of electricity, gas and water; air conditioning (others) | 46 | 23,801 |
Construction | 118 | 60,496 |
Wholesale and retail trade; repair of motor vehicles and bikes | 338 | 94,889 |
Transportation and storage | 280 | 158,667 |
Information and communications | 270 | 16,251 |
Education | 99 | 3,011 |
Health care and social services | 33 | 2,618 |
Other | 3,729 | 675,559 |
Total, including individuals | 19,371 | 2,308,919 |
By the end of 2018, IDGC of the South connected 13,628 consumers to the grid for the total capacity of 575,118 kW.