Increased Reliability Of The Power System
Indicators of the Repair Programme of IDGC of the South Repair | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 |
Overhaul of overhead lines, km | 14,471.6 | 14,776.0 | 14,141.7 | 13,844.4 | 13,890.2 | 16,002.0 |
Overhead line right-of-way tree clearing, Ha | 262.90 | 1,054.70 | 1,050.60 | 1,181.60 | 1,135.73 | 1,277.00 |
Overhaul of transformers and autotransformers, pcs | 41 | 38 | 39 | 41 | 46 | 45 |
Overhaul of switching devices, pcs | 3,977 | 3,604 | 4,264 | 4,410 | 4,125 | 3,254 |
Repair campaign, RUB mn | 781.8 | 1,419.7 | 1,397.6 | 1,533.2 | 1,515.3 | 1,551.0 |
Energy saving and energy efficiency initiatives (2018 projects) Name | Description |
Technology shift | Installation of LED lighting systems |
Equipment conversion or upgrading | Replacement of electrical heaters at the facilities with radiant ones |
Change in employees’ behaviour | Training of the branches’ employees on Basic knowledge of the requirements of the International Standard ISO 50001. Energy Management System. Requirements and directions for use. Internal audits of the energy management system in line with the approved schedule and Standard ISM 80380011-IA/F-5300 049-2015 |
Operational changes | Optimisation of external lighting control by developing and introducing the lighting switching on/off schedule for the on-site territories. Reduction of the heating load in buildings or premises in non-working periods |